The affordable housing site is still moving forward to completion. However, the problems with the connection of supply from Anglian Water have delayed the project. The good news is that these are now resolved and work can be continued with the groundworks and finishing inside the properties. As Anglian Water did not complete connection to the site until 13th January the completion date has now had to be put back until 23rd March.
The process of allocating the properties has begun in relation to the shared ownership dwellings and it is understood the 3 shared ownership properties now have appropriate buyers. The rented properties will be advertised 1 month from a known completion date. Any applicants will see an advert on Home-link and be asked to respond (assuming a pre-registration of the interest has been declared).
Any queries please contact me.
Bob Jewell